The Project
|
Freedom Lifts worked with the architect on this project, providing design assistance during the design phase. Note that due to the job being a State job, the specifications were written to permit any manufacturer to meet the specifications.
After successfully bidding the project, we then worked closely with the contractor. We visited the site multiple times prior to ordering the equipment to help ensure that the concrete and electrical work were done correctly and to save costly changes.
Due to the location of this lift, the lower door is a fire-rated door, while the upper door is Garaventa's standard door with steel infill panels.
|
| |
The Installation
|
The lower door (a 1.5 hour fire-rated door), painted by customer.
Upper door (Standard Garaventa Door), with steel infill panels in standard colors.
Upper door looking in.
Lower door looking in.
Inside shaftway, at lower landing, looking up at upper door.
Garaventa Genesis standard controls. Note the large, illuminated buttons and emergency lights.
|
|